Forum Discussion
Polestar2021
Mar 22, 2022Copper Contributor
Number of assigned resources on tasks
Someone know how to set up a new column to show me the number of assigned resources on tasks? In column Tekst 1 i have drawn numbers in red just for an example. And also i would like to have a colu...
- Mar 24, 2022Polestar2021,
You're welcome and thanks for the feedback.
What exactly do you mean by, "place out resources"? And I'm confused about you desire to show a list of resources not assigned to a task yet. At the top of the Resource Usage view you can see a list of unassigned resources but, those resources may or may not be appropriate for assignment to any given task.
With respect to removing decimals in the days column, if you simply want a whole number of days then replace the t.Text1 line with this:
t.Text1 = Format(t.Duration / 60 / ActiveProject.HoursPerDay, "##") & " days"
John
Vinod_Singh
Mar 25, 2022Copper Contributor
Use a custom field Text and enter the formula in it
[Duration]/[Minutes Per Day] & " days"
and you are done.
Calculation is based on 8 hours per day as defined in project calendar, if you say 7.5 hours, it will change automatically.