I am trying to display the tasks,that I assigned to myself in Project Desktop, to my OS 365 group in TEAMS but when I select the group it says that the group does not have a plan (but I created the Tasks tab in it and I see it). I have MS Project plan 3.  Do you have any advice in where is the problem? I am trying to do this so I will have reminders from Tasks Planner. 

  • The Project tile displayed in Teams is for use with Project for the Web and not MS Project Desktop or Project Online. Your administrator would need to enable Project for the Web in your environment for this feature to work.

2 Replies

  • RodFromm's avatar
    RodFromm
    Steel Contributor
    The Project tile displayed in Teams is for use with Project for the Web and not MS Project Desktop or Project Online. Your administrator would need to enable Project for the Web in your environment for this feature to work.
  • Domlit's avatar
    Domlit
    Brass Contributor

    APansecchi 

     

    The problem is most likely that although you have a project license, your Office365 group (which is a different object in active directory remember) does not and I am unsure if you can even attach licenses for project to a group as its a per user license.