Forum Discussion
allyally123
Aug 26, 2021Tin Contributor
No Publish button on Desktop
For some reason there is no Publish button on the desktop version after I've tried linking the project to PWA. Any help would be greatly appreciated 🙂
1 Reply
- allyally123 --
According to what I see in your attached screenshot, the project is NOT an enterprise project that is stored in the Project Online database. It is an MPP file that is stored in the Documents folder. The Publish button will appear after you save the project to the Project Online database. Hope this helps.