Forum Discussion

LisaPitman's avatar
LisaPitman
Copper Contributor
May 16, 2024
Solved

New to MS Project - Changing start dates not being picked up.

This might be an easy question - I am new to MS Project. In a recent training group when changing the Start Date for a project in Project Information, the new start date is not picked up on the task ...
  • Dale_HowardMVP's avatar
    May 16, 2024
    LisaPitman --

    I can duplicate your problem. You will need to do the following:

    1. Click the File tab and then click the Options tab in the Backstage.
    2. Click the Schedule tab in the Project Options dialog.
    3. Scroll down to the bottom of the Schedule page.
    4. In the Calculation section of the page, select the "On" option to turn on automatic recalculation of your project.
    5. Click the OK button.

    Hope this helps.

Resources