New tasks have calendar 'None' - how to set a default calendar for new tasks?
Hi, For training purposes, I use Project Desktop (version 2309) in offline mode. Before creating any task, I have set the calendar as follows: To reflect the fact that office workers wil...
- Nov 19, 2023
I've got great news for you. An entry of "none" in the Task Calendar field means that task follows the Project Calendar so you're all set.
If a particular task needs to schedule using a different calendar, then you would set the Task Calendar to be the other calendar.
Hope this helps.
John
John-project
Nov 19, 2023Silver Contributor
I've got great news for you. An entry of "none" in the Task Calendar field means that task follows the Project Calendar so you're all set.
If a particular task needs to schedule using a different calendar, then you would set the Task Calendar to be the other calendar.
Hope this helps.
John
nvanmaele
Nov 19, 2023Tin Contributor
Hi John,
Why, that is good news indeed. Thanks for that insight and for your fast reply. Much appreciated.
Why, that is good news indeed. Thanks for that insight and for your fast reply. Much appreciated.
- John-projectNov 20, 2023Silver Contributor