Negative slack
Good afternoon I have a fairly extensive project where a lot of tasks are showing negative slack - up to 300 days! Some are constrained, but i've interrogated it fairly extensively and I can't...
Mar 31, 2023
Robbie --
There are only two causes for negative Total Slack:
1. A successor task has an inflexible constraint, such as Finish No Later Than, and the Finish date of that task has slipped past the FNLT date. This will generate negative Total Slack on that task and on EVERY immediate predecessor task as well.
2. A successor task has a Deadline date and the task's Finish date has slipped past its Deadline date. This will generate negative Total Slack on that task and on EVERY immediate predecessor task as well.
You will need to examine your project for inflexible constraints and Deadline dates, and this will show you the cause of your situation. Hope this helps.
There are only two causes for negative Total Slack:
1. A successor task has an inflexible constraint, such as Finish No Later Than, and the Finish date of that task has slipped past the FNLT date. This will generate negative Total Slack on that task and on EVERY immediate predecessor task as well.
2. A successor task has a Deadline date and the task's Finish date has slipped past its Deadline date. This will generate negative Total Slack on that task and on EVERY immediate predecessor task as well.
You will need to examine your project for inflexible constraints and Deadline dates, and this will show you the cause of your situation. Hope this helps.
robbie_brady
Mar 31, 2023Copper Contributor
Hi Dale
I understand that but when tasks are put in without any predecessors that are automatically assigned a start no earlier than constraint. These tasks then show as critical when really they are not.
Hope I'm making sense.
I understand that but when tasks are put in without any predecessors that are automatically assigned a start no earlier than constraint. These tasks then show as critical when really they are not.
Hope I'm making sense.
- Mar 31, 2023Robbie --
Very odd. Could you share a screenshot so we can see what you are seeing? That would help us to troubleshoot and resolve your problem.