Forum Discussion
Anil_kumar_Anakala
Sep 13, 2022Tin Contributor
Need Project KPI, Cost KPI, Schedule KPI, Work KPI graphical indicators in project online view
Hello all, I Need formulas for KPI's in project online. ex : if schedule kpi is red.......Project kpi has to become red if schedule, work, cost is green ............project kpi has also be...
- Oct 01, 2022I think Kumar, you need to define the contextual meaning of key performance indicators and differentiate them between KPI of PROJECT, SCHEDULE AND WORK. As a matter of fact the difference between the KPI of PROJECT, KPI OF SCHEDULE AND KPI OF WORK is very, very subtle, these are difficult to differentiate. For instance in my on-going PhD thesis, I am using the ACTIVITY START VARIANCE as a KPI for different baseline schedules developed by application of different constraint types of ALAP or ASAP. When there is large activity start variance, the project eventual cost is likely increased. Also a ripple effect is likely set up to affect succeeding activities, though the work quantity might not be affected as such. I am working to post the progress report of this research which is part of an on-going PhD thesis on this platform, hopefully within the a month or two. Some sections of the research addressed some aspects of key performance indicators.
Andrey_Budaragin
Oct 02, 2022Tin Contributor
If you will use numbers 1 for OnTrack; -1 for AtRisk; 0 for InTrouble as KPI Values for schedule, cost, etc, then just multiplying this values will give you overall Project KPI as lower value of the sub-KPIs.
Anil_kumar_Anakala
Oct 04, 2022Tin Contributor
Thank you Andrey for the suggestions. It was useful information to work on it.