Need Parent Id in excel export
I'm using Project2019 Professional Desktop and I wonder if I can have a ParentId (or ParentGUID) field in my export map... I looked around but I didn't find with a meaningful name, but maybe it has a...
Jan 18, 2024
SandroRiz --
The column you are seeking is named Task Summary Name, but there is no GUID version of this field. It simply displays the name of the direct summary task for each task in the project. Sorry, but hope this helps.
The column you are seeking is named Task Summary Name, but there is no GUID version of this field. It simply displays the name of the direct summary task for each task in the project. Sorry, but hope this helps.
- SandroRizJan 18, 2024Tin Contributorthanks Dale, better than nothing