Need help with Project Online - Custom field (text) - PowerBI
Hello, I have created several custom fields (text value, Multiple lines of text) in Project Online, Project level. However, when the fields are imported in powerbi, the carriage return is not recog...
- Feb 22, 2022
Hello Tom_Nguyen ,
This is due to the Project Online reporting API removing all the HTML mark up. See a blog post here:
Paul
Tom_Nguyen
Feb 22, 2022Copper Contributor
Thanks Paul! Will definitely check out your blog posts.
p/s: I'm a fan of yours and can't believe you would one day response to my question !!
p/s: I'm a fan of yours and can't believe you would one day response to my question !!
Paul_Mather
Feb 22, 2022MVP
Thank you for the kind words! Always happy to help the Microsoft Project community where I can.