Need a report or view from Project To Send To Resource Managers for Required Resources
Does Microsoft Project have a view or report that would represent a "resource calendar" that I can send to resource managers showing what resources are needed, the % availability required, and the time period they are needed? I thought the resource graph view might work, but it is limited to only showing a single resource and can't show multiple resources.
1 Reply
- JBLT83 --
I personally would use the Resource Usage view with the timephased grid set to show Weeks. Just a thought. Hope this helps.