Need a report or view from Project To Send To Resource Managers for Required Resources

Does Microsoft Project have a view or report that would represent a "resource calendar" that I can send to resource managers showing what resources are needed, the % availability required,  and the time period they are needed?  I thought the resource graph view might work, but it is limited to only showing a single resource and can't show multiple resources.

  • JBLT83 --

    I personally would use the Resource Usage view with the timephased grid set to show Weeks. Just a thought. Hope this helps.