Forum Discussion
ThomAndrewRoy
Aug 08, 2024Copper Contributor
Multiple Task Update Bug - Fixed Work to Fixed Duration
I am having a recent issue where I am unable to highlight the entire schedule and change everything from fixed duration to fixed work and vice versa. My process is: highlight all tasks (including ...
- Aug 08, 2024Thom --
This is a known bug that has been fixed. You will need to update your copy of Microsoft Project with the latest updates to resolve the bug. Hope this helps.
Aug 08, 2024
Thom --
This is a known bug that has been fixed. You will need to update your copy of Microsoft Project with the latest updates to resolve the bug. Hope this helps.
This is a known bug that has been fixed. You will need to update your copy of Microsoft Project with the latest updates to resolve the bug. Hope this helps.
ThomAndrewRoy
Aug 08, 2024Copper Contributor
This was the answer that I was crossing my fingers and hoping for. Thank you.