Multiple Task Update Bug - Fixed Work to Fixed Duration

I am having a recent issue where I am unable to highlight the entire schedule and change everything from fixed duration to fixed work and vice versa. My process is: highlight all tasks (including ...
  • Dale_HowardMVP's avatar
    Aug 08, 2024
    Thom --

    This is a known bug that has been fixed. You will need to update your copy of Microsoft Project with the latest updates to resolve the bug. Hope this helps.