msproject strange import issue

 
I have a strange issue with msproject.
When I import from excel. The first time it is going oke, but when I add some in the project and import again, then msproject doest level right 1 beneath the inserted  row of mine.
 
Example:
 
import 1 ==> oke
Task1
- item 1
- item 2
Task2 
- item 1
- item 2
Task3
- item 1
- item 2
 
witout inserting an extra item in ms project, and import again from the same file, with merge. ==> oke
But when I do this:
 
Task2 
- item 1
- item 2
- item 3 >>>> this I insert in msproject.
 
When import and merge again, i get this.
 
Task1
- item 1
- item 2
Task2 
- item 1
- item 2
- item 3
Task3   >>>> this level is shifted to the right
- item 1
- item 2
 
what is happening ??

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor
    durana1974,
    What merge key did you use for the import?
    Screen shots of your Excel and Project files would also help.
    John