Forum Discussion

Uli60's avatar
Uli60
Copper Contributor
Sep 14, 2021
Solved

MS Projekt-Bericht: Tabellenüberschriften wiederholen

Hallo, vielleicht kann mir jemand helfen. Ich habe ein Problem: In einem Bericht (Project 2019) habe ich eine ziemlich lange Tabelle, die im Ausdruck über mehrere Seiten geht. Ich möchte, dass die ...
  • Dale_HowardMVP's avatar
    Sep 15, 2021
    Uli60 --

    Thank you for your English explanation of the problem, and for including a couple of screenshots as well. I think I know what you are describing. In Microsoft Word, there is a table option called "Repeat as header row at the top of each page." So, with this option selected, Microsoft Word will repeat the first row (the header row) at the top of the table on each successive page.

    In Microsoft Project, the table functionality in Dashboard reports is very similar to the table functionality in Microsoft Word. But, the functionality is NOT identical. I am sad to report to you that in Microsoft Project, there is NO table option called "Repeat as header row at the top of each page." Sorry, but hope this helps.