Forum Discussion

Jamesp435's avatar
Jamesp435
Brass Contributor
Jan 14, 2022
Solved

MS Projects: Tasks that run over the weekend...

Hi Team  I'm using MS Project (O365).  I have a lot of tasks and for most of the time if a task covers the weekend no work is done (as it should do by default).  My problem, is that a few (but enoug...
  • Dale_HowardMVP's avatar
    Jan 14, 2022
    James --

    What you will need to do is to create two new calendars. One of them will be for Monday through Saturday tasks, and the other will be for Monday through Sunday tasks. Then you will need to need to assign the appropriate calendar as a Task calendar on ONLY to tasks that are not the normal Monday through Friday work schedule. If you need help with how perform either of these actions, please let me know. Hope this helps.

Resources