MS Project VBA to add a button to run a macro...
Hi team A big ask: Does anyone have some VBA code that adds a button to a tab and assigns to a macro when a project file is open, and then hides when the macro is closed. Not sure if I'm allowed...
- Feb 23, 2022Hi John - I'm using MS Project Online Desktop client. Below is the code that is working for me. Like you I'm not an xml person but this works for me.
' Name Proc for Error Handler Message
strProcedure = "sAddCustomRibbon"
Dim ribbonXml As String
ribbonXml = "<mso:customUI xmlns:mso=""http://schemas.microsoft.com/office/2009/07/customui"">"
ribbonXml = ribbonXml + " <mso:ribbon>"
ribbonXml = ribbonXml + " <mso:qat/>"
ribbonXml = ribbonXml + " <mso:tabs>"
ribbonXml = ribbonXml + " <mso:tab id=""tabCustom"" label=""Split / Collapse Tasks"" insertAfterQ=""mso:TabFormat"">"
ribbonXml = ribbonXml + " <mso:group id=""grpSplitCollapse"" label=""Split / Collapse"" autoScale=""true"">"
ribbonXml = ribbonXml + " <mso:button id=""btnSplitTasks"" label=""Split Tasks"" size=""large"" imageMso=""CellsDelete"" onAction=""sSplitTasks""/>"
ribbonXml = ribbonXml + " <mso:button id=""btnCollapseTasks"" label=""Collapse Tasks"" size=""large"" imageMso=""CellsInsertDialog"" onAction=""sCollapseTasks""/>"
ribbonXml = ribbonXml + " </mso:group>"
ribbonXml = ribbonXml + " </mso:tab>"
ribbonXml = ribbonXml + " </mso:tabs>"
ribbonXml = ribbonXml + " </mso:ribbon>"
ribbonXml = ribbonXml + "</mso:customUI>"
ActiveProject.SetCustomUI (ribbonXml)
John-project
Feb 19, 2022Silver Contributor
James,
Are you sure you did it with the ribbon GUI or was it perhaps with the pre-Project 2010 menu driven interface? The old menu driven interface was a lot more flexible. If it was with the ribbon GUI I'd be interested to hear (as might other users) on how XML played into the process.
John
Are you sure you did it with the ribbon GUI or was it perhaps with the pre-Project 2010 menu driven interface? The old menu driven interface was a lot more flexible. If it was with the ribbon GUI I'd be interested to hear (as might other users) on how XML played into the process.
John
James_Price
Feb 19, 2022Brass Contributor
Hi John - the old menus were a joy to change with VBA :-). I found this to give you a flavour of what needs to be done:
Private Sub AddEVMRibbon()
Dim ribbonXml As String
ribbonXml = "<mso:customUI xmlns:mso="http://schemas.microsoft.com/office/2009/07/customui">"
ribbonXml = ribbonXml + " <mso:ribbon>"
ribbonXml = ribbonXml + " <mso:qat/>"
ribbonXml = ribbonXml + " <mso:tabs>"
ribbonXml = ribbonXml + " <mso:tab id=""macroTab"" label=""EVM"" insertAfterQ=""mso:TabFormat"">"
ribbonXml = ribbonXml + " <mso:group id=""testGroup"" label=""Test"" autoScale=""true"">"
ribbonXml = ribbonXml + " <mso:button id=""export_to_excel"" label=""Set EVM Calc Method"" "
ribbonXml = ribbonXml + "imageMso=""DiagramTargetInsertClassic"" onAction=""Set_EVM_Method""/>"
ribbonXml = ribbonXml + " <mso:button id=""get_evm_method"" label=""EVM to Excel"" "
ribbonXml = ribbonXml + "imageMso=""DiagramTargetInsertClassic"" onAction=""evm_to_excel""/>"
ribbonXml = ribbonXml + " </mso:group>"
ribbonXml = ribbonXml + " </mso:tab>"
ribbonXml = ribbonXml + " </mso:tabs>"
ribbonXml = ribbonXml + " </mso:ribbon>"
ribbonXml = ribbonXml + "</mso:customUI>"
ActiveProject.SetCustomUI (ribbonXml)
End Sub
Private Sub AddEVMRibbon()
Dim ribbonXml As String
ribbonXml = "<mso:customUI xmlns:mso="http://schemas.microsoft.com/office/2009/07/customui">"
ribbonXml = ribbonXml + " <mso:ribbon>"
ribbonXml = ribbonXml + " <mso:qat/>"
ribbonXml = ribbonXml + " <mso:tabs>"
ribbonXml = ribbonXml + " <mso:tab id=""macroTab"" label=""EVM"" insertAfterQ=""mso:TabFormat"">"
ribbonXml = ribbonXml + " <mso:group id=""testGroup"" label=""Test"" autoScale=""true"">"
ribbonXml = ribbonXml + " <mso:button id=""export_to_excel"" label=""Set EVM Calc Method"" "
ribbonXml = ribbonXml + "imageMso=""DiagramTargetInsertClassic"" onAction=""Set_EVM_Method""/>"
ribbonXml = ribbonXml + " <mso:button id=""get_evm_method"" label=""EVM to Excel"" "
ribbonXml = ribbonXml + "imageMso=""DiagramTargetInsertClassic"" onAction=""evm_to_excel""/>"
ribbonXml = ribbonXml + " </mso:group>"
ribbonXml = ribbonXml + " </mso:tab>"
ribbonXml = ribbonXml + " </mso:tabs>"
ribbonXml = ribbonXml + " </mso:ribbon>"
ribbonXml = ribbonXml + "</mso:customUI>"
ActiveProject.SetCustomUI (ribbonXml)
End Sub
- John-projectFeb 20, 2022Silver Contributor
James,
Thanks, I'll have to try this when I get some time.Update: Just for reference, the link provided for the schema is no longer active.
John- James_PriceFeb 23, 2022Brass ContributorHi John - that's really strange as we are using it fine.
- John-projectFeb 23, 2022Silver ContributorJames,
Are you sure it copied correctly when you posted? When I click on the link as it appears in your post, I get the message, "the resource you are looking for has been removed, had its name changed, or is temporarily unavailable." Same thing happens if I copy the link and paste into a new browser window.
John