MS Project timeline view...

Hi team  In the MS Project timeline view, can you change the formats to quarter (year) intervals instead of fortnightly ones? Many thanks James 
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Mar 22, 2021
    James -- Click anywhere in the Timeline pane that displays your Timeline view, then click the View tab to display the View ribbon. In the Zoom section of the View ribbon, set the level of zoom you want to see in the Timeline view. Hope this helps.