MS Project timeline labels are wrong...
Hi team In MS Project Gantt, when I tick on the 'Use fiscal year' box, the labels change to the previous year. And this is exactly what's happening in the Timeline view. The starting task is 8 Jan...
- Jun 15, 2021James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
James_Price
Jun 20, 2021Brass Contributor
Hi John
Many thanks for this. I thought if I unticked the 'use starting year in FY numbering' that would be enough but clearly not 🙂
Cheers
James
Many thanks for this. I thought if I unticked the 'use starting year in FY numbering' that would be enough but clearly not 🙂
Cheers
James
John-project
Jun 21, 2021Silver Contributor
James,
You're welcome and thanks for the feedback. Glad you got it cleared up.
John
You're welcome and thanks for the feedback. Glad you got it cleared up.
John