johnsojj -- I can duplicate this behavior in my copy of Microsoft Project. It looks like you have a Fiscal Year scheduled to start on July 1. Click File > Options > Schedule. In the Calendar options section at the top of the dialog, is the Fiscal Year Starts On option set to July? If so, that is why you see this odd schedule in the Timeline view. Hope this helps.
- johnsojjFeb 18, 2021Copper Contributor
Dale_HowardMVP please disregard my previous comment. I think it is because the project timeline is so long. Thanks for your help.
- Feb 18, 2021
johnsojj -- You are more than welcome for the help, my friend!
- johnsojjFeb 18, 2021Copper Contributor
Dale_HowardMVP this fixed this issue on a couple projects, but it does not help on others. It looks like it is set to Quarters. I checked the Timescale and tried setting it to days and months.