MS Project task not changing to correct dates
Hi Community I have a Project where I need to apply weekend working. I have created a new calendar where all dates are 'Working' I then apply this calendar to the task and tick 'Schedulin...
Ash2023
Mar 31, 2023Copper Contributor
Dale_HowardMVP apologies for the delayed response - I didn't seem to get a notification.
In answer to your points:
Do you have a resource assigned to this task? No, I don't have a resource assigned. Below is what I have:
No tasks have been progressed to 100% - Hope the below makes sense, this has never happened to me before so rather baffled!
1. The task date circled in red needs to be Sun 19/03/23
2. Calendar in Task Information is selected to 'Weekend Comms'
3. 'Weekend Comms' calendar has Sun 19/03/23 as a 'Working day' so why is it not changing?
Mar 31, 2023
Your calendar is a 7 work days/week calendar, not a weekend work only calendar. In the custom calendar, update Monday through Friday as nonworking days and this should solve your problem. Hope this helps.