Forum Discussion

Ash2023's avatar
Ash2023
Copper Contributor
Mar 22, 2023

MS Project task not changing to correct dates

Hi Community   I have a Project where I need to apply weekend working.   I have created a new calendar where all dates are 'Working'   I then apply this calendar to the task and tick 'Schedulin...