Forum Discussion
MS Project shows different version when editing
- Mar 07, 2024
Hello,
You are seeing the draft version when going into edit mode and the published version when initially viewing in the web. When in edit mode, if you Publish the project once that is completed, you will then see the same in both edit and view modes.
Paul
Hello,
You are seeing the draft version when going into edit mode and the published version when initially viewing in the web. When in edit mode, if you Publish the project once that is completed, you will then see the same in both edit and view modes.
Paul
- Jul 01, 2024
Hi Paul, don't know if is the same question, but, when open a project, in PWA, the tasks schedule are shown, but when change to Edit mode, all tasks disappear.
If I open the schedule in Desktop, I can't see any task.
Look like, in some projects, the DRAFT version have been lost.
Do you know how fix this?
Thanks