Ms project ressource leveling automatic split

Hello,    I am trying to use the feature of Ms project that automatically split remaining work to do with a resource. Here is a very basic example not leveled yet:  start date of test 1 is...
  • Ignacio_Martin's avatar
    Ignacio_Martin
    Dec 20, 2023
    Hi Sara.
    If the Task type in test 2 is "Fixed Duration", change it to "Fixed Units" or "Fixed Work" (double click on the task > Advanced tab)
    Likewise, try selecting "As Soon As Possible" option in Test2 Constraint type (double click on the task > Advanced tab), because the last image you attached shows a constraint.
    N. Option "Leveling can adjust individual assignments on a task", in this case it does not need to be selected. It can be applied when there is more than one assignment (resource) in the same task.
    I hope I've helped.
    Ignacio