Forum Discussion

James_Price's avatar
James_Price
Brass Contributor
Jun 22, 2021
Solved

MS Project report view tasks in next 30 days...

Hi team  I want to create an report inside MS Project 2019 that shows upcoming tasks in the next 30 days.  I can see there is a filter for 'Tasks starting soon' but cannot find the filter formula.  ...
  • John-project's avatar
    Jun 23, 2021

    James_Price 

    You can view the construct of the "tasks starting soon" filter by going to, View > Data group > Filter selection box > "tasks starting soon".

    As far as creating a 30 day lookahead filter, here is one way to do it. First create two custom date fields
    Date1 = [current date]
    Date2 = [current date] +30
    Then create this filter:

    John

Resources