Forum Discussion
MS Project report view tasks in next 30 days...
- Jun 23, 2021
You can view the construct of the "tasks starting soon" filter by going to, View > Data group > Filter selection box > "tasks starting soon".
As far as creating a 30 day lookahead filter, here is one way to do it. First create two custom date fields
Date1 = [current date]
Date2 = [current date] +30
Then create this filter:John
You can view the construct of the "tasks starting soon" filter by going to, View > Data group > Filter selection box > "tasks starting soon".
As far as creating a 30 day lookahead filter, here is one way to do it. First create two custom date fields
Date1 = [current date]
Date2 = [current date] +30
Then create this filter:
John
John-project Hi John, how to create the following?
First create two custom date fields
Date1 = [current date]
Date2 = [current date] +30
- John-projectJun 18, 2024Silver ContributorNidhi320,
What version of Project are you using? If you don't have the desktop version of Project or Project Online (not Project for the Web) then you won't be able to use the process I outlined above.
John