Forum Discussion
MS Project report view tasks in next 30 days...
- Jun 23, 2021
You can view the construct of the "tasks starting soon" filter by going to, View > Data group > Filter selection box > "tasks starting soon".
As far as creating a 30 day lookahead filter, here is one way to do it. First create two custom date fields
Date1 = [current date]
Date2 = [current date] +30
Then create this filter:John
You can view the construct of the "tasks starting soon" filter by going to, View > Data group > Filter selection box > "tasks starting soon".
As far as creating a 30 day lookahead filter, here is one way to do it. First create two custom date fields
Date1 = [current date]
Date2 = [current date] +30
Then create this filter:
John
thank you John-project, that's very helpful.
I tried with your instructions, and it works for the tasks due within this month. However, the report doesnt show all the tasks meet the criteria. Could you please help on this?
Many thanks!
He
- John-projectFeb 23, 2024Silver ContributorMiss_He,
I need a little more information. What exactly are you trying to accomplish? A screen shot showing where you think certain tasks aren't being flagged might help.
John