Forum Discussion
jeffreymcmillan
Aug 02, 2022Copper Contributor
MS Project report cut off
Hi All I am having issues with a report I created in MS Project. My report falls within the page breaks; however, the report is cut off when I print or pdf. Report view: When printe...
GJENKS1270
Aug 24, 2022Copper Contributor
I'm having the same issue, doesn't matter what printer I use. Started all of the sudden. Doesn't appear to be a solution. Pernille-Eskebo I would really like a solution to this. Otherwise my documents look terrible.
- priya_projectsNov 15, 2023Copper Contributor
There is no solution that I know of to resolve the issue via the print/export command. However, if you fit the report to page by adjusting the zoom and click on 'Copy Report', then you can 'Paste' it in another document in Word, PDF, PPT, Excel or other. The report will be pasted without breaks or missing data. This is how I am working around the problem at the moment and its working fine, hope this helps 🙂