Forum Discussion
jeffreymcmillan
Aug 02, 2022Copper Contributor
MS Project report cut off
Hi All I am having issues with a report I created in MS Project. My report falls within the page breaks; however, the report is cut off when I print or pdf. Report view: When printe...
John-project
Aug 02, 2022Silver Contributor
Might it be as simple as using landscape orientation instead of portrait orientation?
John
jeffreymcmillan
Aug 02, 2022Copper Contributor
John-project unfortunately I am getting the same cutoff in landscape mode. Less is being cut off over it is still being cut off.
- John-projectAug 03, 2022Silver Contributorjeffreymcmillan,
For printing from Project try the Page Setup option that fits the print to 1 page wide by X pages tall.
When I export to PDF I also get a slight bit of cutoff on the right but no loss of data. Same thing when I use Microsoft Print to PDF.
John- jeffreymcmillanAug 08, 2022Copper Contributor
John-project that did worth either. I ended up just shrinking everything down so it doesn't get cut off
- John-projectAug 08, 2022Silver Contributor
I assume you meant to say, "that didn't work either".
I don't have any other suggestions but it sounds like you were able to get what you needed by "shrinking".
John