MS Project: Overallocation not showing in Custom View
Hello, Thank you for reading this. I am using Microsoft Project Online Desktop Client MSO (Version 2308 Build 16.0.16731.20542) 64-bit. It is a Master Project with a Resource Pool. I have creat...
VaibhavSapre
Jul 11, 2024Copper Contributor
Thank you Ignacio_Martin for your investigation and a workaround.
Someone suggested not to use the Resource Pool to avoid this issue. Do you recommend using a single project file to hold 20+ sub-projects with no resource pool?
Someone suggested not to use the Resource Pool to avoid this issue. Do you recommend using a single project file to hold 20+ sub-projects with no resource pool?
Ignacio_Martin
Jul 12, 2024Steel Contributor
- VaibhavSapreJul 12, 2024Copper ContributorThank you for your guidance Ignacio_Martin, I appreciate it!