MS Project Online Desktop Client - Showing Work for Each Resource per Task

Hi All,   Does anyone know of a way to show the level of effort (or work) of individual resources per task? Specifically when a task has multiple resources assigned?   Ideally I'd like to be able...
  • Dale_HowardMVP's avatar
    Mar 24, 2022
    Christian --

    The Task Usage view is the closest that you will get to your reporting requirements. The Work column will show the total amount of work applied to each resource that is assigned to each task. Hope this helps.