MS Project Online Desktop Client - Showing Work for Each Resource per Task
Hi All, Does anyone know of a way to show the level of effort (or work) of individual resources per task? Specifically when a task has multiple resources assigned? Ideally I'd like to be able...
- Mar 24, 2022Christian --
The Task Usage view is the closest that you will get to your reporting requirements. The Work column will show the total amount of work applied to each resource that is assigned to each task. Hope this helps.
Mar 24, 2022
Christian --
The Task Usage view is the closest that you will get to your reporting requirements. The Work column will show the total amount of work applied to each resource that is assigned to each task. Hope this helps.
The Task Usage view is the closest that you will get to your reporting requirements. The Work column will show the total amount of work applied to each resource that is assigned to each task. Hope this helps.