MS Project In MS Teams Export to MS Project Desktop

Hello,   I was wondering if there is a way to export a project made in Teams to MS Project Desktop version. So far I have not been able to find anything that would allow me to do that. I know you c...
  • Dale_HowardMVP's avatar
    Nov 02, 2022
    Ampervor --

    The project to which you are referring in Teams was created in the application known as Project for the Web. As you have found out, there is no direct way to export a P4TW project to the Microsoft Project desktop application. Microsoft's intention, I believe, is for people to export their projects from Microsoft Project to Project for the Web, but not the other way around.

    I have personally experimented with a process to export a P4TW project to Microsoft Project. I first exported the project to an Excel workbook using the built-in export feature. Then I copied and pasted relevant information into an entirely NEW workbook. Then I used the Import Wizard in Microsoft Project to import the project from the new workbook. But it was a TON of work!

    Hope this helps.