Forum Discussion
Ryan_Jarvis
Feb 22, 2024Copper Contributor
MS Project for Web permissions - sharing outside of group membership
Morning,
I wonder if someone could help me with a query on how to grant visibility, ideally read-only permissions, to people within my organisation to projects within MS Project for Web?
I currently have a portfolio (7) of projects for our organisation, each of which are owned by a functional lead. I need to be able to share these project across all functional leads with read-only access to those project they don't own.
The project all have their own M365 group assigned for access but I don't want to add the functional leads to these groups as the group provide access to Teams, SharePoint etc. Is there a way fo achieving this?
Thanks
- There currently isn't a way to do this in Project for the Web. They have to be assigned to the M365 group. Once they have access, they are only limited by their assigned license E3, Plan1, Plan 3 or Plan 5 allows them to do.
1 Reply
- RodFrommSteel ContributorThere currently isn't a way to do this in Project for the Web. They have to be assigned to the M365 group. Once they have access, they are only limited by their assigned license E3, Plan1, Plan 3 or Plan 5 allows them to do.