MS Project (Desktop) - Total % Complete of all Total Number of Active Tasks under a Summary Task
- Apr 25, 2024To those who may be following this thread:
The "answer" to the calculation question is addressed in my response to this same question on the Microsoft Answers forum at:
https://answers.microsoft.com/en-us/msoffice/forum/all/why-does-ms-project-not-calculate-upon-opening/8508dd45-b74d-4319-8301-7167d2858079
John
Hello
You can try the following...
Insert two custom numeric fields and one text field into your task list and enter the formulas and configuration of each field, as shown in the images below, through: Menu > Project > Properties > Custom Fields.
Number1 counts the total number of active subtasks, using the formula (copy and paste): IIf([Active];1;0)
Number2 counts the total number of subtasks completed 100%, using the formula (copy and paste): IIf([% Complete]=100;1;0)
Text1 calculates and rounds the percentage of tasks completed, adding the "%" symbol, only for summary tasks (copy and paste): IIf([Summary];round(100*[Number2]/[Number1]) & "%";"")
N.- If you want you can hide the Number1 and Number2 columns, and rename Text1.
I hope you find it useful.
Ignacio
Ignacio_Martin Hi Ignacio, thought you may be interested in a slight modification I added to your solution. In my case I didn't want any task that is not active to be included in the % calculation. The way it is currently set up it will include the [% Complete] in the calculation even if the [Active] flag is set to "No". I just added an additional test for whether the Active flag (or in my case Flag1) is on and that seems to do what I wanted.
First I updated the formula for the Number 2 field:
Then I updated the formula for the Text field that displays the Task %:
Just wanted to thank you again for posting this solution. It's really helping me a lot!