Forum Discussion
Scheduler_SPP
Mar 01, 2024Copper Contributor
MS Project (Desktop) - Total % Complete of all Total Number of Active Tasks under a Summary Task
I am looking for what I believe is a complex formula. What I am looking to achieve is the following (Example), this would be a new Custom Field: I have a Summary Task with say 10 active sub t...
- Apr 25, 2024To those who may be following this thread:
The "answer" to the calculation question is addressed in my response to this same question on the Microsoft Answers forum at:
https://answers.microsoft.com/en-us/msoffice/forum/all/why-does-ms-project-not-calculate-upon-opening/8508dd45-b74d-4319-8301-7167d2858079
John
Ignacio_Martin
Apr 24, 2024Iron Contributor
Hello
Can you confirm that the automatic calculation option is set to On, in File > Options > Schedule > Calculation > Calculate project after each edit?
Ignacio
Can you confirm that the automatic calculation option is set to On, in File > Options > Schedule > Calculation > Calculate project after each edit?
Ignacio
harmonica_man290
Apr 24, 2024Copper Contributor
- John-projectApr 25, 2024Silver ContributorTo those who may be following this thread:
The "answer" to the calculation question is addressed in my response to this same question on the Microsoft Answers forum at:
https://answers.microsoft.com/en-us/msoffice/forum/all/why-does-ms-project-not-calculate-upon-opening/8508dd45-b74d-4319-8301-7167d2858079
John