MS Project: combine many resources into a team (because total available capacity should be taken)
Hello, I have a project in which development orders arise. These are assigned to development teams. There are xy developers in a team whose availability I would like to maintain individually via "res...
TinaLutz
Aug 04, 2023Copper Contributor
Hi John, great, thanks. I would appreciate if you could help me out: how to create a team resource? And can I take care of absences from individuals or do I have to add all availabilities to one capa?
John-project
Aug 04, 2023Silver Contributor
TinaLutz,
If you're using the desktop version of Project I can show you how but if you're using Project Online or Project for the Web, I'll have to defer to one of my colleagues.
However, one thing you lose with group resources is the ability to individually set up resource calendars for vacations, part time or other deviations from the standard calendar.
John
If you're using the desktop version of Project I can show you how but if you're using Project Online or Project for the Web, I'll have to defer to one of my colleagues.
However, one thing you lose with group resources is the ability to individually set up resource calendars for vacations, part time or other deviations from the standard calendar.