Forum Discussion
MS Project Capabilities
- Jul 15, 2022Bruce --
In spite of the confusion, you basically have three choices for a PPM tool from Microsoft:
1. Project for the Web
2. Microsoft Project desktop application only
3. Microsoft Project desktop with Project Online
To answer your questions, Project for the Web cannot meet any of those five needs.
Microsoft Project desktop only can meet needs #2 and #5.
Microsoft Project desktop with Project Online can meet all five of those needs. Keep in mind that if you want to use Microsoft Project with Project Online, your organization will probably need help setting up the system and training people how to use it. Hope this helps.
Bruce --
While waiting for your reply, I did some research on LinkedIn and found a Bruce Tweedie in Australia. If that is you, I don't think I can help you as the time zone differences would be too challenging. And if you are in Australia, I would encourage you to reach out to Sensei Project Solutions. I used to work for their US branch, but they have multiple locations in Australia, with top notch people. Hope this helps.
- BruceTweedieJul 19, 2022Copper ContributorHi Dale, Yes indeed that would be me. And yes the time zones can be very challenging. I have a son in NY so I do understand that. Thanks for the referral to Sensei, I'll reach out to them. Cheers ... Bruce
- BruceTweedieJul 20, 2022Copper ContributorHi Dale, can you please clarify what you mean by "Microsoft Project desktop with Project Online". When I look at the various products available to me, MS talks about Plans 1, 3, and 5: https://www.microsoft.com/en-au/microsoft-365/project/compare-microsoft-project-management-software?activetab=tabs%3aprimaryr1
How does that align with your product description? Thanks ... Bruce- Jul 20, 2022
Bruce --
The Plan 1 subscription provides access to Project for the Web, and provides team member access to Project Online. Project Plan 3 provides project manager access to Project Online, and provides a license for Project Online Professional (aka the Microsoft Project desktop application). Project Plan 5 provides Administrator access to Project Online and provides a license for Project Online Professional. Hope this helps.