MS Project can you enter a custom field for a project and not a task...
- Aug 29, 2022
Hi James_Price ,
From your question I assume you are referring to standalone MS Project desktop (Project Pro / Project Standard etc.)? If that is the case, Project level custom fields are only available when Project is connected to Project Server / Project Online. All you can do at the project / file level with standalone MS Project is add properties to the file (File > Info > Project Information > Advanced Properties).
Hope that helps
Paul
Hi James_Price ,
From your question I assume you are referring to standalone MS Project desktop (Project Pro / Project Standard etc.)? If that is the case, Project level custom fields are only available when Project is connected to Project Server / Project Online. All you can do at the project / file level with standalone MS Project is add properties to the file (File > Info > Project Information > Advanced Properties).
Hope that helps
Paul
- Paul_MatherAug 30, 2022MVP
Hi James_Price,
No problem. If you're looking at Project Server, the latest version is the Project Server Subscription Editon: https://docs.microsoft.com/en-us/project/new-features-capabilities-project-server-subscription-edition
Paul
- James_PriceAug 31, 2022Brass ContributorThanks for that Paul.
James