Forum Discussion

James_Price's avatar
James_Price
Brass Contributor
Aug 29, 2022
Solved

MS Project can you enter a custom field for a project and not a task...

Hi team Is is possible to have a custom field for a project in MS Project rather than a Task.  E.g. if I wanted the project to have a City name associated with it, I don't want to have to have a tas...
  • Paul_Mather's avatar
    Aug 29, 2022

    Hi James_Price ,

    From your question I assume you are referring to standalone MS Project desktop (Project Pro / Project Standard etc.)? If that is the case, Project level custom fields are only available when Project is connected to Project Server / Project Online. All you can do at the project / file level with standalone MS Project is add properties to the file (File > Info > Project Information > Advanced Properties).

    Hope that helps

    Paul