Forum Discussion

JBLT-77's avatar
JBLT-77
Iron Contributor
May 22, 2022
Solved

MS Project Calculating Duration Incorrectly

When I set a fixed duration task to start on 5/25 and finish on 6/7, this is a duration of 10 days. MS Project for some reason however, is displaying a duration of 12 days. This is incorrect. I don't...
  • John-project's avatar
    May 22, 2022
    John Bacon,
    I'm guessing you did not change the working calendar to reflect the 6 hour work day. By default, each work day is 8 hours (8:00 AM to 12:00 PM and 1:00 PM to 5:00 PM). The number of default days from 5/25/22 through 6/7/22, including the non-working memorial day, is 9. So 9 of the default 8 hour working days equals 72 hours. However, you have re-defined a "day" as 6 hours so 72 divided by 6 equals, wait for it, 12 "days".

    The fact that resources may only be 75% efficient is not relevant for Project's scheduling calculation. That's something you will have to take into account when you estimate task durations and assign resources.

    Hope this helps.
    John