Forum Discussion
MS Project: Calculate risk with formula
Hello Community,
I want to use a custom field that shows me when the end date is less than today (past) or equal to today and the % Completed is less than 100%. I tried the following but it didn't work:
[End]<= Now() And [% Completed]<100%
If the date is less than or equal to today and the % Completed is less than 100%, it should show me a red flag, otherwise is green:
In this example, the 1st, 2nd. and 4th. lines should be green, because it is not 100% completed, but the finish date is greater then today.
The 3rd should be green, because is 100% completed.
The 5th line should be red, because the date is less or equal today and it is not 100% completed.
Can anyone help me?
Thanks a lot!
Joao
Use this formula IIf([Finish]<=[Current Date] And [% Complete]<100,"Yes","No") and add graphical indicators for "Yes" and "No"
2 Replies
- PlannersPlaceBrass Contributor
Use this formula IIf([Finish]<=[Current Date] And [% Complete]<100,"Yes","No") and add graphical indicators for "Yes" and "No"
- Joao_SilveiraCopper ContributorMany thanks, it worked perfectly!