Hello, I am a first time user and poster here and I apologize in advance if I my question has already been answered previously. I want to use MS Project and Teams as a collaboration tool for my t...
Aug 04, 2022
Steve --
This is a really good question, so there is no need to apologize for asking it. The Project icon refers to the Project for the Web application. Hope this helps.
This is a really good question, so there is no need to apologize for asking it. The Project icon refers to the Project for the Web application. Hope this helps.
Steve2325
Aug 10, 2022Copper Contributor
Dale_HowardMVP Thank you for the response. Does this mean MS teams can only work hand in hand with MS Project for the Web?
I find that Project on the web does not have all the tools such as Project Desktop (i.e. The Web version only allows for FS dependency).
- Aug 10, 2022Steve --
Yes, your assumptions are true. Project for the Web has only a very small set of features found in the Microsoft Project desktop application. Project for the Web is intended for small and simple projects, while the Microsoft Project desktop application can handle every type of project from small and simple projects to large and complex projects.
So, if you want to use a project management tool with Teams, Project for the Web is your options. Sorry, but hope this helps.- Steve2325Aug 22, 2022Copper Contributor
How do you go about using MS Project for the Web in Teams - Do you use other apps in MS teams to follow-up on activities, to-do lists, etc? If so, can you provide a couple you prefer working with?
- Aug 22, 2022Steve --
If you use Project for the Web in teams, you can display your project for team members to view and update their progress using the Teams user interface. I do not personally use Project for the Web as its feature set is way too limited for my needs. Perhaps others in this group who use Project for the Web can answer your questions. Hope this helps.