Forum Discussion
aiod70
Jul 27, 2024Copper Contributor
MS Project allocation of resources
Hi, When using ms project, is there any way I can have a maximum work time for a people resource. My issue is this: I am planning a diving job using welders. We have 6 welders but only 1 can dive ...
aiod70
Jul 27, 2024Copper Contributor
Thanks John,
I'll give this a go. It looks like it should work. The real problem for me is that the max unit for a resource is a variable that changes with each task. So I was hoping to find a way that would weight or load the resource for each task.
I'll give your way a go though.
Thanks again,
Adrian
John-project
Jul 27, 2024Silver Contributor
Adrian,
Ordinarily the max units for a resource would determine the availability of the resource but yours is a unique case. Each resource is 100% available, assuming divers are full time and no off-days/vacation are in play. So in your case the defining time period is the duration of the dive (Duration field), and NOT the resource availability.
John
Ordinarily the max units for a resource would determine the availability of the resource but yours is a unique case. Each resource is 100% available, assuming divers are full time and no off-days/vacation are in play. So in your case the defining time period is the duration of the dive (Duration field), and NOT the resource availability.
John