MS Project actual time overwrites time
In project 2016 PRO, why does the Actual time overwrite the 'planned' time??
John-project
Apr 09, 2021Silver Contributor
I assume you mean that when you enter an actual start, Project automatically updates the scheduled start to the actual start date. That's the way it works. There is no point in having a schedule date that is out of sync with what really happened.
Project has a whole set of baseline fields that exist to capture the original plan. Those fields can then be used to compare the current plan with the original as the plan is executed. But in order to take advantage of that functionality, the user needs to set a baseline once the plan is ready for execution but before execution starts.
If what I explained above is not what you mean, then please elaborate on exactly what you mean by "overwriting time" and we'll explain that.
Project has a whole set of baseline fields that exist to capture the original plan. Those fields can then be used to compare the current plan with the original as the plan is executed. But in order to take advantage of that functionality, the user needs to set a baseline once the plan is ready for execution but before execution starts.
If what I explained above is not what you mean, then please elaborate on exactly what you mean by "overwriting time" and we'll explain that.
AnnickV2706
Apr 13, 2021Copper Contributor
Hello!
Sorry, I made a mistake in my message…
What I’m trying to solve is why the ‘Actual work’ (and not ‘actual time’…) overwrites the ‘planned’ work? It makes no sense to me.
If I update the ‘actual work’ in my PWA timesheet or directly in Project, the ‘work’ (planned) numbers get adjusted with the ‘actual work’ I just entered. Is it a question of configuration? Is there something I should do to stop that? It is a serious issue for my project and my client…
Txs!
Sorry, I made a mistake in my message…
What I’m trying to solve is why the ‘Actual work’ (and not ‘actual time’…) overwrites the ‘planned’ work? It makes no sense to me.
If I update the ‘actual work’ in my PWA timesheet or directly in Project, the ‘work’ (planned) numbers get adjusted with the ‘actual work’ I just entered. Is it a question of configuration? Is there something I should do to stop that? It is a serious issue for my project and my client…
Txs!
- testingtheApr 21, 2021Copper Contributor
AnnickV2706 Actual hours - for example from timesheets - will always replace planned hours. You may wish to set a baseline if you want to compare planned hours vs. actual hours historically.
- John-projectApr 13, 2021Silver Contributor
Well, what exactly is your configuration? Are you in a Project Server environment? What are your task types (i.e. fixed work, fixed duration or fixed units)? Are resources assigned? If so, how many and what kind (i.e. work, cost or material)? How are you entering actual work?
I know, that's whole lot of questions, but until we can better understand what you have, we can't provide much help. A screen shot may also help.
John