MS Project 2019 Clearing Resource Baseline Work

We recently migrated to MS Project 2019.  We've noticed that when we replace a resource on a task using Assign Resources, the original resource's baseline work is cleared or reduced.  On our previous Project the new resource would retain all the replaced resource's baseline work. 

 

Is there an option somewhere to remove the clearing of a baseline from a task resource during a replace?  Or does one of the CU's fix this issue?

  • John-project's avatar
    John-project
    Silver Contributor

    RCook1959,
    First of all, no, there is no option to clear the baseline when a resource is changed. Baseline fields are static, it takes direct user action to set a baseline, change a baseline or clear a baseline.

    How exactly are you replacing the resource? Do you remove the original resource before assigned the new resource? Do both resource have the same Base Calendar and Max Units and are they the same type (e.g. Work)?

    What is your version and build? The latest is version 2308 (build 16731.20234 CTR).

    John

    • RCook1959's avatar
      RCook1959
      Copper Contributor

      John-project

      I normally use the "Assign Resources" dialog to replace resources. There are a couple of other ways but that's the primary method.

       

      The more I think about the problem, the more I think the process was changed by Microsoft because the new resource was not present during baseline. As such, a new resource should not contain the baseline originally laid in during planning.

       

      I would have liked for the process to keep the original resource with their baseline timephasing intact and zero out the remaining work. The new resource would be added with the remaining work and no baseline. There is a way around this but it takes longer to do as you can't just replace the existing resource and feel everything is good to go.. 

      • John-project's avatar
        John-project
        Silver Contributor
        RCook1959,
        Okay, it finally dawned on me that you are referring to the Assignment baseline data, not the Task baseline date. Indeed, assignment level baseline information doesn't exist until a resource, existing or new, is actually assigned to a task.

        If you have a process to get what you want, I'd go with that. I think what you are asking is beyond the intent of how Project operates but you might consider submitting a request via the feedback portal, "I have a suggestion".

        John