Forum Discussion
Molalenge
Dec 11, 2023Brass Contributor
MS Project 2019 and Planner
Hi, Can one connect MS Project 2019 with MS Planner? What are the steps. Thanks, Teshome
Molalenge
Dec 21, 2023Brass Contributor
Dale,
Thank you for getting back to me. Planner has an export Excel option. However, it doesn't filter specific tasks under the planner; any suggestions?
Regards,
Teshome
Thank you for getting back to me. Planner has an export Excel option. However, it doesn't filter specific tasks under the planner; any suggestions?
Regards,
Teshome
Dec 21, 2023
Molalenge --
If you apply the Board view in Planner, you can click the Filter button in the upper right corner of the page. There are a number of built-in filtering options on the menu. If none of those work for you, however, you would need to filter the data in Excel. Just a thought. Hope this helps.
If you apply the Board view in Planner, you can click the Filter button in the upper right corner of the page. There are a number of built-in filtering options on the menu. If none of those work for you, however, you would need to filter the data in Excel. Just a thought. Hope this helps.