MS Project 2019 and Planner
Hi, Can one connect MS Project 2019 with MS Planner? What are the steps. Thanks, Teshome
Dec 12, 2023
Teshome --
You can only connect an MS Planner project in Microsoft Project is your project is an enterprise project stored in Project Online. There is no way to connect a desktop only project (saved as an MPP file) to a Planner project. Hope this helps.