MS Project 2019- can one view two separate project files in two separate screens

Hi,

 

I have an MS project for 2019, and I can see two separate projects on one monitor. First, I open the two project files that I want to compare and then VIEW-ARRANGE ALL on the ribbon tab. Can you open two projects on two separate screens? What are the steps? 

 

Thanks.

Teshome

6 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    Teshome,
    It sounds like you want to compare the two files. Why not use the Compare Projects utility found under the Reports tab of the ribbon?
    John
    • Molalenge's avatar
      Molalenge
      Brass Contributor

      John-project 

       

      Thank you for your response. I have MS Project 2019 and i don't see this option under the Report Tab of the ribbon. Thanks. Teshome

      • John-project's avatar
        John-project
        Silver Contributor

        Molalenge,

        I have Project Pro 2019 version 2311 (Build 17029.20108 CTR). This is my ribbon:

        John

  • Molalenge --

    No, there is no built-in method for displaying two projects, each on its own screen. Others in this group can offer you some very convoluted workarounds to this problem, but there is no direct built-in method for doing this. Hope this helps.