Forum Discussion
genglehardt
Aug 03, 2021Copper Contributor
MS Project 2016 row height problem
Suddenly the row heights of new projects is about 8 letters tall rather than the normal 1 letter high. I tried adjusting the row heights via the prescribed View-Tables-Entry-Edit route. I can make ...
- Jun 10, 2024Mary --
Thanks for sharing the screenshot. You have two columns to the right of the Finish column, whose column width is narrowed to practically nothing. That is causing the extreme height of the column headers row. Either set the column width of those two columns to 0 to hide them, or widen them so that you can see the names of those columns. That should solve your problem. Hope this helps.
Aug 10, 2021
genglehardt --
Thanks very, very much for sharing those two screenshots. It is easy to see why you have run into this little problem. In your blank project, you have the Bar Rollup view applied, which is why you see the very tall task rows in your project. If you apply the Gantt Chart view, the task rows will return to their default height. I think you may have erroneously set the Bar Rollup view as your default view for all new blank projects. Instead, I think you need the Gantt Chart view set as the default view. To do this, click File > Options. On the General page of the dialog, click the Default View pick list and select the Gantt Chart view. Click the OK button to apply the changes. Now create a new blank project and you should see the task rows are the normal height. Hope this helps.
Thanks very, very much for sharing those two screenshots. It is easy to see why you have run into this little problem. In your blank project, you have the Bar Rollup view applied, which is why you see the very tall task rows in your project. If you apply the Gantt Chart view, the task rows will return to their default height. I think you may have erroneously set the Bar Rollup view as your default view for all new blank projects. Instead, I think you need the Gantt Chart view set as the default view. To do this, click File > Options. On the General page of the dialog, click the Default View pick list and select the Gantt Chart view. Click the OK button to apply the changes. Now create a new blank project and you should see the task rows are the normal height. Hope this helps.
genglehardt
Aug 10, 2021Copper Contributor
That worked like a charm!!! Thank you, thank you. This problem was driving me crazy. I don't think i have ever used the roll up view.
Again, thanks for your help.
Gary
- Aug 10, 2021Gary -- You are more than welcome for the help, my friend. If my response solved your problem, would you kindly mark it as the best response? Thanks!
- MaryMcMichaelJun 10, 2024Copper Contributor
Dale_HowardMVP The first row in the MS Project Gantt chart, for whatever reason, has gotten very deep (like 10 rows deep), which causes an issue in being able to see more task rows below that. How can I reduce the size of that first 'title' row for each column?
- Jun 10, 2024Mary --
Please share a screenshot so that I can see what is going on in your project. Thanks!