Forum Discussion
SarahvdWant
Jan 30, 2024Copper Contributor
MS Project - Resource graph - double availability line per resource
We use MS Project to ensure that all resources have enough work and are not overloaded.
It is important to take into account the personal working hours that are entered in the calendars of the resour...
LH_B123
Jul 15, 2024Brass Contributor
RubenMaartense I have an ongoing support case going on with Microsoft about this issue. I few days ago they wrote that the issue would be solved in the upcoming release for Microsoft Project Online Desktop Client. I asked back for the specific version number in which they expected the issue to be solved and I am awaiting an answer now.
RubenMaartense
Jul 18, 2024Copper Contributor
Thank you for the update. When you have more info, please post it here so we know what to expect.